Scope of Project:
The scope of work for this project consisted of constructing twelve (12) 20 foot diameter, two (2) 30 foot diameter, and three (3) 40 foot diameter sheet pile cells for a new barge unloading facility. This facility was part of the power station environmental compliance (FGD) project on the Ohio River, just south of Stuebenville, Ohio. In addition to the cell construction, Brayman’s contract included minor dredging, scour protection, access walkways, reinforced concrete cell caps, and E crane platforms. |