Freedom Road Bridge Project Due to Wrap-up This Fall

Work has recently been completed on the Snake Run Road Bridge, Structure S-35950, one of three bridges Brayman was subcontracted to build by Independence Excavating in 2016.  All remaining efforts are now being focused on the third and final bridge, Structure S-35950, on Park Quarry Road. In the course of this construction season Brayman has already completed the driven piles, abutments, precast concrete beam erection, and deck pour.

TyBot, by Advanced Construction Robotics, was utilized to tie the deck slabs on both the Snake Run and Park Quarry Road Bridges. Use of the autonomous rebar-tying robot resulted in a labor and schedule savings over conventional methods.

This project is currently set to wrap-up in the fall of 2018.