Meadow Park Dam
Location:Crossville, TN
Owner: City of Crossville
General Contractor: Brayman Construction Corp.
Value: $3.6 Million
Date Complete: July 2012
Brayman was contracted for the structural remediation of Meadow Park Dam to provide stability and to eliminate leakage through and under dam.
This will be achieved by:
-
Installing 6 temporary siphons to de-water and control the 270-acre reservoir
-
Installing a temporary cofferdam to work on the structure “in the dry”
-
Mechanical removal of all deleterious and damaged concrete and spall areas from the submerged face of the dam and spillways and repair or replacement of concrete in these areas
-
Installing a 225cy concrete cap
-
Filling the entire structure with shotcrete
-
Installing 51 high-capacity post-tension anchors tying the structure to the bedrock
-
Pressure grouting the entire structure to seal existing lift joints
-
Installing 2,100cy buttress downstream of the structure
Brayman also performed the removal of all construction staging, falsework, and cleaning of site.