Thank you to the Team Brayman IT Department for putting on a great lunch and learn about the importance of Cyber Security.
The Westbound pier column forms and reinforcing steel have been recently placed, and are being prepared for another mass concrete pour. The Eastern abutment footers have been formed and are ready to pour, and the Eastbound column form is ready to be formed and poured soon.
The westbound River Bridge at our I-64 Nitro, WV Joint Venture is nearing its completion. 1,345 LF of the 1,425 LF bridge deck has been poured and the bridge is on schedule to be open to motorists this fall.
Brayman team members have recently been spotted working alongside some local celebrities, a nesting pair of Osprey, and two hatchlings. The Osprey, a very powerful bird of prey, was listed as extirpated, locally extinct, in Pennsylvania in 1979. However, over the last several decades, the state has undertaken a significant revitalization effort to reintroduce the […]