Team Brayman has successfully completed the Phase 2 structural steel erection on the VDOT C94 Twin Bridge Replacements Project in Amelia, VA. The erection involved setting the girders and diaphragms over top of Business Route 360, and a Norfolk Southern railroad track. The operation was completed with the use of our 222 Crane as pictured. This activity could not have been performed successfully without the pre-planning and teamwork of our project staff. This puts the project on course to begin constructing the super structure with the goal to place deck concrete in late March-early April.