Brayman has completed the drilling of 40 of 132 (9 5/8″) micropiles to support foundations for a new Norfolk Southern Railroad Bridge near Federal Street in Pittsburgh. Brayman is a subcontractor for the Trumbull Corporation project. Due to phasing for track restrictions, 48 micropiles must be drilled under the existing bridge in less than 15 […]
Posts
E.S. Wagner Company, working for Norfolk Southern Railroad, recently contracted Brayman’s Foundation Division for a $1.6M project in Bellevue, OH. The scope of work will be performed near “active” railroad tracks, in three different phases, and entails the furnishing and installation of caissons and secant pile walls. The walls will consist of a series of […]