Complex Heavy Civil Infrastructure

Alternative Delivery

Partnering with engineering firms and owners on alternative delivery contracts such as design-build, progressive design build, integrated project delivery, and CMGC or Early Contractor involvement projects.

Alternative Delivery

Brayman Construction Corporation (BCC) was contracted by the Virginia Department of Transportation (VDOT) to provide design, Quality Control/Quality Assurance Management (QC/QAM), and construction services for the I-77 Over Route 606 Bridge Replacement project in Bland County, VA.
Brayman Construction was awarded a $20.5 million design-build Accelerated Bridge Construction (ABC) contract for a multi-bridge project consisting of 8 bridge deck replacements and 2 specialized overlays along the busy I-77 and I-64 corridor in Charleston, WV that had to be completed in an extremely short timeframe.
Brayman Construction Corporation and Trumbull Corporation, a Joint Venture (BTJV), was contracted to provide design and construction services for the $254 million U.S. 35/I-64 Interchange – Nitro Interchange Design-Build Project. Brayman served as the lead contractor in this Joint Venture.
Brayman and Shoreline Foundation, Inc. of Miami, Florida, were contracted by Kingston Wharves Limited to design and reconstruct Berth 7 at the Port of Kingston in Kingston, Jamaica. This project was a Joint Venture in which Brayman was the lead contractor.
The Rodney Staton Memorial Bridge project involved the design-build rehabilitation of a 630-LF, three span structure spanning R.D. Bailey Lake.